TASIČ, Tadej ;BUCHMEISTER, Borut ;AČKO, Bojan . The development of advanced methods for scheduling production processes. Strojniški vestnik - Journal of Mechanical Engineering, [S.l.], v. 53, n.12, p. 844-857, august 2017. ISSN 0039-2480. Available at: <https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/>. Date accessed: 19 nov. 2024. doi:http://dx.doi.org/.
Tasič, T., Buchmeister, B., & Ačko, B. (2007). The development of advanced methods for scheduling production processes. Strojniški vestnik - Journal of Mechanical Engineering, 53(12), 844-857. doi:http://dx.doi.org/
@article{., author = {Tadej Tasič and Borut Buchmeister and Bojan Ačko}, title = {The development of advanced methods for scheduling production processes}, journal = {Strojniški vestnik - Journal of Mechanical Engineering}, volume = {53}, number = {12}, year = {2007}, keywords = {production process planning; deterministic sequencing; scheduling; priority rules; }, abstract = {The planning of dates and capacities belongs to the area of production management. Scheduling represents the allocation of scarce sources to tasks in a definite period of time. So it is about a process of deciding, with the goal of optimization, about one or more criteria. In general it includes rough (long-term), medium-term and detailed (short-term) planning. The last of these has the greatest importance because of a direct connection with operational effectiveness. Some developed scheduling procedures are presented in the paper i.e., the priority (dispatching) rules, the filtered-beam search, and the constraint-guided heuristic search. All this is substantiated with described examples. }, issn = {0039-2480}, pages = {844-857}, doi = {}, url = {https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/} }
Tasič, T.,Buchmeister, B.,Ačko, B. 2007 August 53. The development of advanced methods for scheduling production processes. Strojniški vestnik - Journal of Mechanical Engineering. [Online] 53:12
%A Tasič, Tadej %A Buchmeister, Borut %A Ačko, Bojan %D 2007 %T The development of advanced methods for scheduling production processes %B 2007 %9 production process planning; deterministic sequencing; scheduling; priority rules; %! The development of advanced methods for scheduling production processes %K production process planning; deterministic sequencing; scheduling; priority rules; %X The planning of dates and capacities belongs to the area of production management. Scheduling represents the allocation of scarce sources to tasks in a definite period of time. So it is about a process of deciding, with the goal of optimization, about one or more criteria. In general it includes rough (long-term), medium-term and detailed (short-term) planning. The last of these has the greatest importance because of a direct connection with operational effectiveness. Some developed scheduling procedures are presented in the paper i.e., the priority (dispatching) rules, the filtered-beam search, and the constraint-guided heuristic search. All this is substantiated with described examples. %U https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/ %0 Journal Article %R %& 844 %P 14 %J Strojniški vestnik - Journal of Mechanical Engineering %V 53 %N 12 %@ 0039-2480 %8 2017-08-18 %7 2017-08-18
Tasič, Tadej, Borut Buchmeister, & Bojan Ačko. "The development of advanced methods for scheduling production processes." Strojniški vestnik - Journal of Mechanical Engineering [Online], 53.12 (2007): 844-857. Web. 19 Nov. 2024
TY - JOUR AU - Tasič, Tadej AU - Buchmeister, Borut AU - Ačko, Bojan PY - 2007 TI - The development of advanced methods for scheduling production processes JF - Strojniški vestnik - Journal of Mechanical Engineering DO - KW - production process planning; deterministic sequencing; scheduling; priority rules; N2 - The planning of dates and capacities belongs to the area of production management. Scheduling represents the allocation of scarce sources to tasks in a definite period of time. So it is about a process of deciding, with the goal of optimization, about one or more criteria. In general it includes rough (long-term), medium-term and detailed (short-term) planning. The last of these has the greatest importance because of a direct connection with operational effectiveness. Some developed scheduling procedures are presented in the paper i.e., the priority (dispatching) rules, the filtered-beam search, and the constraint-guided heuristic search. All this is substantiated with described examples. UR - https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/
@article{{}{.}, author = {Tasič, T., Buchmeister, B., Ačko, B.}, title = {The development of advanced methods for scheduling production processes}, journal = {Strojniški vestnik - Journal of Mechanical Engineering}, volume = {53}, number = {12}, year = {2007}, doi = {}, url = {https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/} }
TY - JOUR AU - Tasič, Tadej AU - Buchmeister, Borut AU - Ačko, Bojan PY - 2017/08/18 TI - The development of advanced methods for scheduling production processes JF - Strojniški vestnik - Journal of Mechanical Engineering; Vol 53, No 12 (2007): Strojniški vestnik - Journal of Mechanical Engineering DO - KW - production process planning, deterministic sequencing, scheduling, priority rules, N2 - The planning of dates and capacities belongs to the area of production management. Scheduling represents the allocation of scarce sources to tasks in a definite period of time. So it is about a process of deciding, with the goal of optimization, about one or more criteria. In general it includes rough (long-term), medium-term and detailed (short-term) planning. The last of these has the greatest importance because of a direct connection with operational effectiveness. Some developed scheduling procedures are presented in the paper i.e., the priority (dispatching) rules, the filtered-beam search, and the constraint-guided heuristic search. All this is substantiated with described examples. UR - https://www.sv-jme.eu/sl/article/the-development-of-advanced-methods-for-scheduling-production-processes/
Tasič, Tadej, Buchmeister, Borut, AND Ačko, Bojan. "The development of advanced methods for scheduling production processes" Strojniški vestnik - Journal of Mechanical Engineering [Online], Volume 53 Number 12 (18 August 2017)
Strojniški vestnik - Journal of Mechanical Engineering 53(2007)12, 844-857
© The Authors, CC-BY 4.0 Int. Change in copyright policy from 2022, Jan 1st.
The planning of dates and capacities belongs to the area of production management. Scheduling represents the allocation of scarce sources to tasks in a definite period of time. So it is about a process of deciding, with the goal of optimization, about one or more criteria. In general it includes rough (long-term), medium-term and detailed (short-term) planning. The last of these has the greatest importance because of a direct connection with operational effectiveness. Some developed scheduling procedures are presented in the paper i.e., the priority (dispatching) rules, the filtered-beam search, and the constraint-guided heuristic search. All this is substantiated with described examples.