Realistic Lead Times of Operations and Efficiency of the PPC System

1879 Ogledov
555 Prenosov
Izvoz citacije: ABNT
STARBEK, Marko ;GRUM, Janez ;KUŠAR, Janez .
Realistic Lead Times of Operations and Efficiency of the PPC System. 
Strojniški vestnik - Journal of Mechanical Engineering, [S.l.], v. 48, n.2, p. 98-111, july 2017. 
ISSN 0039-2480.
Available at: <https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/>. Date accessed: 20 dec. 2024. 
doi:http://dx.doi.org/.
Starbek, M., Grum, J., & Kušar, J.
(2002).
Realistic Lead Times of Operations and Efficiency of the PPC System.
Strojniški vestnik - Journal of Mechanical Engineering, 48(2), 98-111.
doi:http://dx.doi.org/
@article{.,
	author = {Marko  Starbek and Janez  Grum and Janez  Kušar},
	title = {Realistic Lead Times of Operations and Efficiency of the PPC System},
	journal = {Strojniški vestnik - Journal of Mechanical Engineering},
	volume = {48},
	number = {2},
	year = {2002},
	keywords = {PPC-systems; lead times; funnel models; flow diagrams; },
	abstract = {The practical efficiency of commercially available PPC (production planning and control) systems [1] and [2] depends to a great extent on the implementation of operations’ lead times determination which is based on estimated or calculated lead times of workplaces. This paper presents a method for calculating the average lead times of workplaces. The average lead times of workplaces, found in the interval P, gives a realistic picture of the order flow through workplaces, and these data are the basis for the implementation of the realistic operations’ lead times determination in the next (P+1) interval. With the proposed method for calculating lead times a transition from static to dynamic orders’ lead times determination is accomplished.},
	issn = {0039-2480},	pages = {98-111},	doi = {},
	url = {https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/}
}
Starbek, M.,Grum, J.,Kušar, J.
2002 July 48. Realistic Lead Times of Operations and Efficiency of the PPC System. Strojniški vestnik - Journal of Mechanical Engineering. [Online] 48:2
%A Starbek, Marko 
%A Grum, Janez 
%A Kušar, Janez 
%D 2002
%T Realistic Lead Times of Operations and Efficiency of the PPC System
%B 2002
%9 PPC-systems; lead times; funnel models; flow diagrams; 
%! Realistic Lead Times of Operations and Efficiency of the PPC System
%K PPC-systems; lead times; funnel models; flow diagrams; 
%X The practical efficiency of commercially available PPC (production planning and control) systems [1] and [2] depends to a great extent on the implementation of operations’ lead times determination which is based on estimated or calculated lead times of workplaces. This paper presents a method for calculating the average lead times of workplaces. The average lead times of workplaces, found in the interval P, gives a realistic picture of the order flow through workplaces, and these data are the basis for the implementation of the realistic operations’ lead times determination in the next (P+1) interval. With the proposed method for calculating lead times a transition from static to dynamic orders’ lead times determination is accomplished.
%U https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/
%0 Journal Article
%R 
%& 98
%P 14
%J Strojniški vestnik - Journal of Mechanical Engineering
%V 48
%N 2
%@ 0039-2480
%8 2017-07-07
%7 2017-07-07
Starbek, Marko, Janez  Grum, & Janez  Kušar.
"Realistic Lead Times of Operations and Efficiency of the PPC System." Strojniški vestnik - Journal of Mechanical Engineering [Online], 48.2 (2002): 98-111. Web.  20 Dec. 2024
TY  - JOUR
AU  - Starbek, Marko 
AU  - Grum, Janez 
AU  - Kušar, Janez 
PY  - 2002
TI  - Realistic Lead Times of Operations and Efficiency of the PPC System
JF  - Strojniški vestnik - Journal of Mechanical Engineering
DO  - 
KW  - PPC-systems; lead times; funnel models; flow diagrams; 
N2  - The practical efficiency of commercially available PPC (production planning and control) systems [1] and [2] depends to a great extent on the implementation of operations’ lead times determination which is based on estimated or calculated lead times of workplaces. This paper presents a method for calculating the average lead times of workplaces. The average lead times of workplaces, found in the interval P, gives a realistic picture of the order flow through workplaces, and these data are the basis for the implementation of the realistic operations’ lead times determination in the next (P+1) interval. With the proposed method for calculating lead times a transition from static to dynamic orders’ lead times determination is accomplished.
UR  - https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/
@article{{}{.},
	author = {Starbek, M., Grum, J., Kušar, J.},
	title = {Realistic Lead Times of Operations and Efficiency of the PPC System},
	journal = {Strojniški vestnik - Journal of Mechanical Engineering},
	volume = {48},
	number = {2},
	year = {2002},
	doi = {},
	url = {https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/}
}
TY  - JOUR
AU  - Starbek, Marko 
AU  - Grum, Janez 
AU  - Kušar, Janez 
PY  - 2017/07/07
TI  - Realistic Lead Times of Operations and Efficiency of the PPC System
JF  - Strojniški vestnik - Journal of Mechanical Engineering; Vol 48, No 2 (2002): Strojniški vestnik - Journal of Mechanical Engineering
DO  - 
KW  - PPC-systems, lead times, funnel models, flow diagrams, 
N2  - The practical efficiency of commercially available PPC (production planning and control) systems [1] and [2] depends to a great extent on the implementation of operations’ lead times determination which is based on estimated or calculated lead times of workplaces. This paper presents a method for calculating the average lead times of workplaces. The average lead times of workplaces, found in the interval P, gives a realistic picture of the order flow through workplaces, and these data are the basis for the implementation of the realistic operations’ lead times determination in the next (P+1) interval. With the proposed method for calculating lead times a transition from static to dynamic orders’ lead times determination is accomplished.
UR  - https://www.sv-jme.eu/sl/article/realistic-lead-times-of-operations-and-efficiency-of-the-ppc-system/
Starbek, Marko, Grum, Janez, AND Kušar, Janez.
"Realistic Lead Times of Operations and Efficiency of the PPC System" Strojniški vestnik - Journal of Mechanical Engineering [Online], Volume 48 Number 2 (07 July 2017)

Avtorji

Inštitucije

  • University of Ljubljana, Faculty of Mechanical Engineering, Slovenia
  • University of Ljubljana, Faculty of Mechanical Engineering, Slovenia
  • University of Ljubljana, Faculty of Mechanical Engineering, Slovenia

Informacije o papirju

Strojniški vestnik - Journal of Mechanical Engineering 48(2002)2, 98-111
© The Authors, CC-BY 4.0 Int. Change in copyright policy from 2022, Jan 1st.

The practical efficiency of commercially available PPC (production planning and control) systems [1] and [2] depends to a great extent on the implementation of operations’ lead times determination which is based on estimated or calculated lead times of workplaces. This paper presents a method for calculating the average lead times of workplaces. The average lead times of workplaces, found in the interval P, gives a realistic picture of the order flow through workplaces, and these data are the basis for the implementation of the realistic operations’ lead times determination in the next (P+1) interval. With the proposed method for calculating lead times a transition from static to dynamic orders’ lead times determination is accomplished.

PPC-systems; lead times; funnel models; flow diagrams;